A plain-English glossary of the technical and contractual terms that recur in renewable-energy bankability — yield and performance (P50/P75/P90, Performance Ratio, specific yield, CUF), operations and maintenance (availability, response time, MTBF), contracts (defects liability period, delay vs performance liquidated damages, serial defect, retention) and finance (DSCR, independent engineer).
Yield and performance
- P50 / P75 / P90 — probabilities of exceedance: the energy yield expected to be exceeded with 50%, 75% or 90% probability. Lenders size debt against P90 (a conservative case), not P50 (the central estimate).
- Performance Ratio (PR) — the ratio of a plant’s actual output to the output theoretically possible from the irradiance it received — a measure of how efficiently the plant converts available sunlight, independent of resource.
- Temperature-corrected PR — a PR adjusted to a reference temperature, used for short assessment windows (e.g. commissioning) so results are comparable regardless of the weather during the test.
- Specific yield — annual energy generated per unit of installed capacity (kWh/kWp) — a resource-dependent benchmark for comparing sites.
- CUF / PLF — Capacity Utilisation Factor / Plant Load Factor: actual generation as a percentage of the theoretical maximum if the plant ran at rated capacity continuously.
- Transposition factor — the factor converting global horizontal irradiance to the irradiance in the plane of the modules, accounting for tilt, tracking and ground-reflected (albedo) light.
- Degradation / LID / LETID / PID — mechanisms by which module output declines: long-term degradation (~0.4–0.5%/yr), light-induced and light-and-elevated-temperature-induced degradation, and potential-induced degradation.
Operations and maintenance
- Availability (technical / contractual / energy-based) — the share of time a plant is able to generate. Technical availability applies no exclusions; contractual applies an agreed set; energy-based weights lost time by the irradiance at which it occurred.
- Minimum irradiance threshold — the irradiance level (typically ~50–70 W/m²) below which availability is not counted, since little energy is at stake.
- Response time — the acknowledgement-plus-intervention time an O&M provider guarantees after a fault — usually the guaranteed metric, whereas repair time is not.
- MTBF / MTTR — Mean Time Between Failures / Mean Time To Repair — reliability and maintainability measures for equipment.
Contracts
- Defects Liability Period (DLP) — the period after handover (typically 12–24 months) during which the contractor must remedy defects at its own cost.
- Delay LD vs Performance LD — liquidated damages for late completion (delay LDs) versus for failing to meet a guaranteed performance ratio (performance LDs) — drafted separately and capped.
- Serial defect — the same root-cause defect appearing across a threshold share of a component population (e.g. ≥5% of panels), obliging rectification of all units — even those not yet failed.
- Retention — a percentage of each payment withheld as security, ideally released only once the plant is generating and performing.
- Taking-over / COD — the point at which the plant is accepted and commercial operation begins, transferring risk and triggering warranty and performance obligations.
Finance and roles
- DSCR — Debt-Service-Cover Ratio: cash available for debt service divided by debt due. A minimum below 1 in any year means the project cannot service its debt that year.
- Independent Engineer / Lender’s Technical Advisor — the specialist a lender appoints to verify the project’s technical assumptions and certify construction progress before drawdowns.
- Owner’s Engineer — the specialist the sponsor appoints to review design and witness key construction stages and tests on its behalf.
- Force majeure — an exceptional, unforeseeable event beyond a party’s control that suspends obligations — typically treated as a neutral risk with each party bearing its own costs.
